TG World Provides Update Regarding Tindalo Well Workover Schedule
Tuesday, Aug 31, 2010
TG World Energy Corp. (TSX VENTURE:TGE) ("TG World" or the "Company") announces that project partner and operator of Service Contract 54A in the Philippines, Nido Petroleum Ltd. ("Nido"), has provided the following update on the Tindalo-1 well."Nido Petroleum Limited, as Operator of Service Contract 54A ("SC 54A"), is pleased to advise that the mobilisation of the material and equipment required for the Tindalo-1 well intervention and remediation programme has commenced with results expected from the workover before the end of September.
-- The support vessel M/V Pacific Ariki started loading the material
required for the well intervention in Singapore on 27 August and will
mobilise to the Tindalo location via Labuan, Malaysia;
-- Well testing will continue until the Pacific Ariki delivers its cargo to
the Aquamarine Driller and well re-entry operations commence, which is
expected within 2 weeks, subject to weather.
-- Diagnostic logging undertaken as the first step in the well intervention
will determine the selection of the remediation option and all items
necessary for the three options under consideration are being mobilised
to site.
-- The well intervention is expected to take 10-17 days to complete.
|
|
Well testing is continuing at the field location and the following can be confirmed since the previous update on 19 August 2010:
-- Disposal of some 278,000 barrels of the produced water stored on the FSO
was completed successfully during a production shutdown from 22-28
August; and
-- Some 183,000 barrels of oil (@ 60 degrees F) are now in the storage
tanks of the FSO.
|
|
Nido will provide a further update on progress once well re-entry operations commence."